Within a rooftop PV project at an industrial facility in Istanbul, the Suryon team provided inverter installation, transformer and switchgear substation setup, along with electro-mechanical works, site coordination, and acceptance/commissioning support.
Scope of Work:
- Inverter installation and AC/DC connections
- Transformer and switchgear substation setup (protection–metering schemes, MV/LV connections)
- Pre-commissioning tests and technical documentation
- Site coordination and interface with contractors/suppliers
Project Summary:
- System Type: Rooftop PV
- Location: Istanbul, Turkey
- Our Role: Inverter, transformer & switchgear setup; electro-mechanical installation; site coordination; technical support for acceptance
Key Outcomes:
- Complete and safe infrastructure including the AC/MV side
- Standard-compliant protection–metering and commissioning tests
- Contribution to the facility’s energy-efficiency and sustainability goals